CUP: I11B20000360001
REALIZZAZIONE DEL PONTE PROVVISORIO PER LA VIABILITÃ ALTERNATIVA AL PONTE STORICO "BURIANO".
SUMMARY OF THE PROJECT
REALIZZAZIONE DEL PONTE PROVVISORIO SUL FIUME ARNO. INTERVENTO RIPROGRAMMATO COME DA DGRT N. 791/2022 E DA NOTA MIMS REG. UFFICIALE N. U.0014875-18-08-2022
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 0.73 km
- Achieved
- 0.73 km
Funding monitored
€ 3,100,000.00
of which cohesion funds
€ 3,100,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3100000.00 |
Payments monitored
€ 2,141,339.01
of which cohesion funds
€ 2,141,339.01
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 8717.48 | 8717.48 | 0 |
2021 | 35525.04 | 44242.52 | 1 |
2022 | 118004.39 | 162246.91 | 5 |
2023 | 1970592.10 | 2132839.01 | 68 |
2024 | 8500.00 | 2141339.01 | 69 |
State of progress
Open
Expected start: 09/01/2023
Effective start: 09/01/2023
Expected end: 11/11/2023
Effective end: 11/09/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI AREZZO
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI AREZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale