CUP: B54H14000860004
RISANAMENTO DELLA PRESA SORGENTE PLENTENBACH E RINNOVO DELLA'IMPIANTO DI APPROVVIGIONAMENTO ACQUA POTABILE GSCHON
SUMMARY OF THE PROJECT
RISANAMENTO DELLA PRESA SORGENTE PLENTENBACH E RINNOVO DELLA'IMPIANTO DI APPROVVIGIONAMENTO ACQUA POTABILE GSCHON
Implementation indicator
Estensione della rete
- Target
- 1.77 km
- Achieved
- 1.77 km
Funding monitored
€ 815,327.90
of which cohesion funds
€ 326,131.16
Given name | Amount |
---|---|
Development and Cohesion Fund | 326131.16 |
Province | 326131.20 |
Municipality | 163065.54 |
Payments monitored
€ 815,327.90
of which cohesion funds
€ 326,131.16
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 815327.90 | 815327.90 | 100 |
State of progress
Completed
Expected start: 20/04/2015
Effective start: 20/04/2015
Expected end: 07/06/2016
Effective end: 07/06/2016
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- COMUNE DI MONTAGNA SULLA STRADA DEL VINO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC P.A. BOLZANO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
FITODEPURATORE DI CASIGNANO - MONTAGNA | € 479,835 |