CUP: C51H14000150002
ADEGUAMENTO SISMICO DELLA SEDE MUNICIPALE
SUMMARY OF THE PROJECT
ADEGUAMENTO SISMICO DELLA SEDE MUNICIPALE
Implementation indicator
Superficie oggetto di intervento
- Target
- 540 mq
- Achieved
- 540 mq
Funding monitored
€ 341,758.72
of which cohesion funds
€ 341,758.72
Given name | Amount |
---|---|
Development and Cohesion Fund | 341758.72 |
- Economies:
- € 2,940.00
Payments monitored
€ 341,758.72
of which cohesion funds
€ 341,758.72
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 105312.75 | 105312.75 | 30 |
2017 | 181725.95 | 287038.70 | 83 |
2018 | 54720.02 | 341758.72 | 100 |
State of progress
Completed
Expected start: 09/10/2015
Effective start: 09/10/2015
Expected end: 01/09/2017
Effective end: 01/09/2017
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI PICCIANO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici