CUP: J83E12000030006
DECIMOMANNU - LAVORI DI ADEGUAMENTO IMPIANTI SPORTIVI VIA DELLE AIE
SUMMARY OF THE PROJECT
DECIMOMANNU - LAVORI DI ADEGUAMENTO IMPIANTI SPORTIVI VIA DELLE AIE
This project is no longer active and is therefore excluded from totals and search results
Funding monitored
€ 164,866.30
of which cohesion funds
€ 123,649.73
Given name | Amount |
---|---|
Development and Cohesion Fund | 123649.73 |
Municipality | 41216.57 |
- Economies:
- € 35,133.70
Payments monitored
€ 164,866.30
of which cohesion funds
€ 123,649.73
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 10538.97 | 10538.97 | 6 |
2013 | 0 | 10538.97 | 6 |
2014 | 0 | 10538.97 | 6 |
2015 | 0 | 10538.97 | 6 |
2016 | 0 | 10538.97 | 6 |
2017 | 122424.32 | 132963.29 | 80 |
2018 | 31410.40 | 164373.69 | 99 |
2019 | 462.60 | 164836.29 | 99 |
2020 | 30.01 | 164866.30 | 100 |
State of progress
Completed
Expected start: 03/11/2015
Effective start: 03/11/2015
Expected end: 30/11/2017
Effective end: 20/12/2017
Entities
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2017-18 with the team “SportivaMente” of “IIS ENRICO MATTEI” of Decimomannu, CAGLIARI.
Read the Monithon report.
View the creative output.
Read the Monithon report.
View the creative output.