CUP: F91B03000310001
LAVORI DI COSTRUZIONE DELLA SS 195 TRATTO CAGLIARI-PULA LOTTI 1A, 3A E OPERE CONNESSE SUD
SUMMARY OF THE PROJECT
LAVORI DI COSTRUZIONE DELLA SS 195 TRATTO CAGLIARI-PULA LOTTI 1A, 3A E OPERE CONNESSE SUD
Implementation indicator
Estensione in lunghezza
- Target
- 15.30 km
- Achieved
- 10.20 km
Funding monitored
€ 201,804,670.18
of which cohesion funds
€ 56,676,000.00
Given name | Amount |
---|---|
European Union | 72565000.00 |
Development and Cohesion Fund | 56676000.00 |
Another public source | 72563670.18 |
Payments monitored
€ 106,988,494.42
of which cohesion funds
€ 42,878,263.54
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 419268.43 | 419268.43 | 0 |
2009 | 516792.22 | 936060.65 | 0 |
2010 | 759403.62 | 1695464.27 | 0 |
2011 | 2297886.68 | 3993350.95 | 1 |
2012 | 4434732.05 | 8428083.00 | 4 |
2013 | 1654677.87 | 10082760.87 | 4 |
2014 | 3233492.66 | 13316253.53 | 6 |
2015 | 10367078.79 | 23683332.32 | 11 |
2016 | 16285637.17 | 39968969.49 | 19 |
2017 | 10790830.48 | 50759799.97 | 25 |
2018 | 8015560.83 | 58775360.80 | 29 |
2019 | 558342.70 | 59333703.50 | 29 |
2020 | 24324798.11 | 83658501.61 | 41 |
2021 | 10697855.64 | 94356357.25 | 46 |
2022 | 10260522.72 | 104616879.97 | 51 |
2023 | 2371614.45 | 106988494.42 | 53 |
State of progress
Open
Expected start: 22/12/2011
Effective start: 22/12/2011
Expected end: 09/01/2025
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- ANAS SOCIETA PER AZIONI
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale