CUP: J21B20000160001
¿REALIZZAZIONE DI COLLEGAMENTO DELL¿ASSE ATTREZZATO DI PESCARA E ADEGUAMENTO SVINCOLO S.S. 714¿ ADEGUAMENTO SVINCOLO S.S:714 - SUBINTERVENTO 3
SUMMARY OF THE PROJECT
L' INTERVENTO HA IL FINE DI MIGLIORARE E RAZIONALIZZARE IL TRAFFICO URBANO NELLA ZONA SUD DELLA CITTÃ A CONFINE CON FRANCAVILLA AL MARE ED ELIMINARE I DETRATTORI AMBIENTALI CHE CONTRASTANO CON I VALORI NATURALISTICO/PAESAGGISTICI DELLA CONTIGUA PINETA DANNUNZIANA.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Download project
Funding monitored
€ 6,800,000.00
of which cohesion funds
€ 6,800,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 6800000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/05/2023
Effective start: 02/04/2024
Expected end: 27/05/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI PESCARA
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale