CUP: E96J17000240002

RITTMEYER EFFICIENTAMENTO ENERGETICO 2017

SUMMARY OF THE PROJECT

IL PROGETTO MIRA A RIDURRE I CONSUMI ENERGETICI ALL'INTERNO DELLA SEDE ISTITUZIONALE, SITA IN TRIESTE, VIALE MIRAMARE N. 119, MIGLIORANDO LE PRESTAZIONI DELL'INVOLUCRO E CONTEMPERANDO GLI INTERVENTI CON I VINCOLI ED I LIMITI PRESENTI NELLA STRUTTURA. LA STRUTTURA Ê DI CARATTERE STORICO ED ARCHITETTONICO ED Ê SITUATA IN ZONA SOGGETTA A VINCOLO PAESAGGISTICO ED IDROGEOLOGICO. IL PROGETTO SI COMPLETA CON L'ADOZIONE DI SISTEMI INTELLIGENTI DI CONTROLLO DELL'ILLUMINAZIONE

Updated on 31/12/2018
Public cost € 407,500.00
Given name Amount
European Union203750.00
Revolving Fund142625.00
Region61125.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 15/06/2018
Effective start: not available
Expected end: 15/12/2018
Effective end: not available

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO

Theme

Territory

Entities

Planning body
SERVIZIO TECNOLOGIE ED INVESTIMENTI
Beneficiario
DIREZIONE GENERALE

Programming area

European Regional Development Fund (ERDF)
2014-2020 EU Structural Funds
Programme
POR FESR FRIULI VENEZIA-GIULIA
Axis
SOSTENERE LA TRANSIZIONE VERSO UN'ECONOMIA A BASSE EMISSIONI
Specific objective
Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili

Other projects in territory