CUP: J97D18000100003
LAVORI PER LA RIDUZIONE DEI CONSUMI DI ENERGIA PRIMARIA PRESSO LA PALESTRA DELLA SCUOLA SECONDARIA D
SUMMARY OF THE PROJECT
LAVORI PER LA RIDUZIONE DEI CONSUMI DI ENERGIA PRIMARIA PRESSO LA PALESTRA DELLA SCUOLA SECONDARIA DI PRIMO GRADO A FELETTO UMBERTO
Implementation indicators
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 156,357 KWh/a
- Achieved
- 156,357 KWh/a
Potenza installata
- Target
- 503.10 KW
- Achieved
- 503.10 KW
Superficie oggetto di intervento
- Target
- 978.57 mq
- Achieved
- 978.57 mq
- Slide 1
- Slide 2
- Slide 3
Funding monitored
€ 298,394.73
of which cohesion funds
€ 298,394.73
Given name | Amount |
---|---|
European Union | 149197.38 |
Revolving Fund | 104438.11 |
Region | 44759.24 |
- Other resources - Private:
- € 214,576
Payments monitored
€ 283,727.57
of which cohesion funds
€ 283,727.56
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 236532.64 | 236532.64 | 79 |
2021 | 42273.71 | 278806.35 | 93 |
2022 | 4921.22 | 283727.57 | 95 |
State of progress
Completed
Expected start: 01/06/2020
Effective start: 24/07/2020
Expected end: 30/09/2021
Effective end: 01/02/2021
Entities
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF FRIULI VENEZIA-GIULIA
- Axis
- SOSTENERE LA TRANSIZIONE VERSO UN'ECONOMIA A BASSE EMISSIONI
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili