CUP: D11E05000000008

PIASTRA PORTUALE DI TARANTO

SUMMARY OF THE PROJECT

PROGETTAZIONE, COSTRUZIONE E GESTIONE

Implementation indicator

Superficie oggetto di intervento

Target
20,000 MQ
Achieved
20,000 MQ
Updated on 31/12/2020
Funding monitored € 181,600,550.11 of which cohesion funds € 33,600,000.00
Given name Amount
European Union4000000.00
Development and Cohesion Fund33600000.00
Another public source144000550.11
Other resources - Private:
€ 37,544,000
Payments monitored € 15,660,772.53 of which cohesion funds € 10,369,398.96
Year Amount Cumulative amount Percentage on public financing
20059376.179376.170
200609376.170
200709376.170
200809376.170
200909376.170
201009376.170
201109376.170
201209376.170
201309376.170
201409376.170
201509376.170
20169831612.669840988.835
201709840988.835
201809840988.835
20195819783.7015660772.538

State of progress

Open
Expected start: 30/08/2013
Effective start: 30/08/2013
Expected end: 01/04/2020
Effective end: not available

Type

Theme

Territory

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PIASTRA PORTUALE DI TARANTO
Line
Infrastrutture
Action
Infrastrutture portuali