CUP: B24E15000770002
DGR 182/2015. PROGRAMMA DI EFFICIENTAMENTO E RIFUNZIONALIAZZIONE DEGLI IMPIANTI DI DEPURAZIONE DELLE STAZIONI DI SOLLEVAMENTO DEI REFLUI URBANI RICADENTI NE COMUNI COSTIERI DELLA REGIONE CALABRIA. COMUNE DI JOPPOLO
Funding monitored
€ 26,411.50
of which cohesion funds
€ 26,411.50
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 26411.50 |
Payments monitored
€ 26,411.50
of which cohesion funds
€ 26,411.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 8803.83 | 8803.83 | 33 |
2017 | 17607.67 | 26411.50 | 100 |
State of progress
Completed
Expected start: 19/10/2015
Effective start: 19/10/2015
Expected end: 30/11/2015
Effective end: 30/11/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Trattamento delle acque (potabili)
Territory
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI JOPPOLO
- Beneficiary
- COMUNE DI JOPPOLO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Programme
- PROGRAMMA PAC CALABRIA
- Line
- Nuove Azioni
- Action
- Programmi di efficientamento e rifunzionalizzazione degli impianti di depurazione delle stazioni di sollevamento dei reflui urbani nei comuni costieri della regione Calabria