CUP: G34I06000230002

ENAC/RC10B - AEROPORTO DI REGGIO CALABRIA. ADEGUAMENTO E POTENZIAMENTO DELLE INFRASTRUTTURE IN AMBITO AIR SIDE - II° LOTTO - RESA TXT 11, VIABILITà PERIMENTRALE, MANUFATTI, TRATTAMENTO ACQUE

Updated on 29/02/2020
Funding monitored € 2,799,100.00 of which cohesion funds € 2,799,100.00
Given name Amount
European Union2099325.00
Revolving Fund (National co-financing)488163.04
Region211611.96
Payments monitored € 1,111,457.72 of which cohesion funds € 0.00
Year Amount Cumulative amount Percentage on public financing
2011275807.72275807.729
2012459560.00735367.7226
2013376090.001111457.7239

State of progress

Open
Expected start: 30/12/2010
Effective start: not available
Expected end: 30/06/2013
Effective end: not available

Type

Theme

Territory

Entities

Planning body
REGIONE CALABRIA
Implementing body
SOCIETA' DI GESTIONE PER L'AEROPORTO DELLO STRETTO SOCIETA' IN LIQUIDAZIONE
REGIONE CALABRIA
Beneficiary
SOCIETA' DI GESTIONE PER L'AEROPORTO DELLO STRETTO SOCIETA' IN LIQUIDAZIONE
REGIONE CALABRIA
Executor
REGIONE CALABRIA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF CALABRIA
Axis
Asse VI - Reti e Collegamenti per la Mobilità
Operational objective
Potenziare i Sistemi Regionali Portuale, Aeroprtuale e Iintermodale - Logistico.