CUP: B94D17000000001

PROGETTAZIONE PROLUNGAMENTO M5 A MONZA

SUMMARY OF THE PROJECT

Prolungamento M5 a Monza

Implementation indicator

Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate

Target
10 KM
Achieved
0 KM
Updated on 31/12/2018
Public cost € 15,996,373.39
Given name Amount
Development and Cohesion Fund15996373.39
Economies:
€ 3,626.61
Payments € 3,444,976.83
Year Amount Cumulative amount Percentage on public financing
20183444976.833444976.8321

State of progress

Open
Expected start: 01/08/2017
Effective start: 14/09/2017
Expected end: 15/09/2020
Effective end: not available

Type

Theme

Territory

Entities

Planning body
COMUNE DI MILANO
Implementing body
MM SPA
Beneficiario
COMUNE DI MILANO

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PATTO PER LO SVILUPPO CITTA' DI MILANO
DCF strategic sector
Infrastrutture
DCF area axis
Trasporto sostenibile urbano