CUP: I19E18000010007

RIFACIMENTO RETI ACQUEDOTTO DI VIA OLGIATE INTERNA (DA EX ENFAPI A VIA DALCA), VIA PLINIO (TRATTO TRA VIA XX SETTEMBRE E VIA CAMPO SPORTIVO), VIA OLGIATE, VIA PER GIRONICO

SUMMARY OF THE PROJECT

ADEGUAMENTO E RISTRUTTURAZIONE DI ALCUNI TRATTI DELLA RETE DI ACQUEDOTTO COMUNALE, SOGGETTI A RICORRENTI E PROBLEMATICHE PERDITE IDRICHE. L¿INTERVENTO CONSISTE NELLA SOSTITUZIONE DELLE VECCHIE RETI IN AMIANTO CEMENTO, CON TUBAZIONI IN GHISA SFEROIDALE, COMPRESO IL RIFACIMENTO DEGLI ALLACCIAMENTI D¿UTENZA ED IL POSIZIONAMENTO DEI CONTATORI ALL¿ESTERNO DELLE PROPRIETà. LUNGHEZZA RETI DA RISTRUTTURARE: VIA OLGIATE INTERNA (160M), VIA PLINIO (370M), VIA OLGIATE (270M), VIA PER GIRONICO (150M). TOTALE INTERVENTO PARI A 950M.

Implementation indicator

Beneficiari/Popolazione Beneficiaria

Target
9,900
Achieved
-
Updated on 31/08/2018
Public cost € 274,750.00
Given name Amount
Revolving Fund80750.00
Development and Cohesion Fund194000.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Not started
Expected start: 04/11/2019
Effective start: not available
Expected end: 04/09/2020
Effective end: not available

Type

Theme

Territory

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO OPERATIVO FSC AMBIENTE
DCF strategic sector
Ambiente
DCF area axis
Servizio idrico integrato