CUP: F77E15000080005

MOLO B - ADEGUAMENTO AMBIENTALE E RIQUALIFICAZIONE DELLA BANCHINA EMILIA IN CANALE INDUSTRIALE OVEST.

SUMMARY OF THE PROJECT

L'INTERVENTO PREVEDE LA RIQUALIFICAZIONE DELLA BANCHINA DENOMINATA EMILIA, ATTRAVERSO LA REALIZZAZIONE DI UNA BARRIERA IMPERMEABILE LUNGO LO SVILUPPO LONGITUDINALE, IL CONTESTUALE CONSOLIDAMENTO STRUTTURALE, LA REALIZZAZIONE DI UN SISTEMA DI RACCOLTA E TRATTAMENTO DELLE ACQUE METEORICHE E LA SISTEMAZIONE DELLA PAVIMENTAZIONE A TERGO DELLA BANCHINA STESSA.

Implementation indicator

Estensione dell'intervento in lunghezza

Target
257 M
Achieved
257 M
Updated on 31/12/2020
Public cost € 10,765,769.90
Given name Amount
Development and Cohesion Fund10765769.90
Payments € 6,118,655.28
Year Amount Cumulative amount Percentage on public financing
20161647816.021647816.0215
2017514791.212162607.2320
20181700204.983862812.2135
20192245794.126108606.3356
202010048.956118655.2856

State of progress

Open
Expected start: 19/07/2020
Effective start: 16/05/2016
Expected end: 30/11/2020
Effective end: 12/11/2018

Type

Theme

Territory

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC AMBIENTE
DCF strategic sector
Ambiente
DCF area axis
Recupero dei siti industriali e dei terreni contaminati - bonifiche