CUP: F54H15001050001
08IR317/G1 -COMPLETAMENTO INTERVENTI DI CONSOLIDAMENTO PARETE ROCCIOSA E DIFESA DELL'ABITATO DI TORRIANA
SUMMARY OF THE PROJECT
COMPLETAMENTO DEGLI INTERVENTI DI CONSOLIDAMENTO E DI DIFESA DELL'ABITATO DI TORRIANA MEDIANTE IMPIEGO DI OPERE PASSIVE E ATTIVE IN PARETE
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 100 num
- Achieved
- 100 num
Funding monitored
€ 500,000.00
of which cohesion funds
€ 500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 500000.00 |
Payments monitored
€ 412,407.94
of which cohesion funds
€ 412,407.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 117509.59 | 117509.59 | 23 |
2021 | 264941.62 | 382451.21 | 76 |
2022 | 0 | 382451.21 | 76 |
2023 | 29956.73 | 412407.94 | 82 |
State of progress
Open
Expected start: 09/09/2019
Effective start: 13/09/2019
Expected end: 05/10/2020
Effective end: 28/10/2020
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- AGENZIA REGIONALE PER LA SICUREZZA TERRITORIALE E LA PROTEZIONE CIVILE
- Beneficiary
- COMMISSARIO STRAORDINARIO PER IL RISCHIO IDROGEOLOGICO EMILIA ROMAGNA
- Executor
- MORANI SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same theme
EFFICIENTAMENTO ENERGETICO IMPIANTI DI PUBBLICA ILLUMINAZIONE - SOSTITUZIONE CORPI ILLUMINANTI | € 57,411 |
Same type of investment
MANUTENZIONE STRAORDINARIA DELLE STRADE COMUNALI DI MONTAGNA | € 353,895 |