CUP: E73H19000290003
INTERVENTO DI CONSOLIDAMENTO GEOTECNICO DEL VERSANTE RETROSTANTE IL BORGO ANTICO DI CAMPOMARINO
SUMMARY OF THE PROJECT
CAMPOMARINO Ê UBICATO SU UN¿AREA SUBPIANEGGIANTE COSTITUITA DA UN TERRAZZO (ALTO MORFOLOGICO) DI ORIGINE MARINA, A UNA QUOTA DI CIRCA 52 M SLM. IL TERRAZZO Ê DELIMITATO, A MONTE, DA UNA PENDICE AD ELEVATA ACCLIVITà , CHE DEGRADA VERSO LA FASCIA COSTIERA
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 85 num
- Achieved
- 0 num
Funding monitored
€ 2,000,000.00
of which cohesion funds
€ 2,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2000000.00 |
Payments monitored
€ 4,800.00
of which cohesion funds
€ 4,800.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 4800.00 | 4800.00 | 0 |
State of progress
Open
Expected start: 14/05/2023
Effective start: not available
Expected end: 27/08/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE-DIREZIONE GENERALE PER LA SALVAGUARDIA DEL TERRITORIO E DELLE ACQUE
- Implementing body
- COMUNE DI CAMPOMARINO
- Beneficiary
- STRUTTURA COMMISSARIALE STRAORDDELEGATA ALLA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REG MOLISE
- Executor
- DITTA¿ I.M.O.S. SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico