CUP: D89G19000860001
CENTRO SPORTIVO OLIMPICO ROMA - RIFACIMENTO IMPIANTO DI CLIMATIZZAZIONE PALESTRA
SUMMARY OF THE PROJECT
RIFACIMENTO IMPIANTO DI CLIMATIZZAZIONE DELLA PALESTRA POLIFUNZIONALE
Implementation indicator
Superficie oggetto di intervento
- Target
- 600 mq
- Achieved
- 608 mq
Funding monitored
€ 56,851.35
of which cohesion funds
€ 56,851.35
Given name | Amount |
---|---|
Development and Cohesion Fund | 56851.35 |
- Economies:
- € 23,148.65
Payments monitored
€ 56,851.35
of which cohesion funds
€ 56,851.35
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 56851.35 | 56851.35 | 100 |
State of progress
Completed
Expected start: 30/01/2020
Effective start: 15/06/2020
Expected end: 02/03/2020
Effective end: 14/07/2020
Entities
- Planning body
- STATO MAGGIORE DELL'ESERCITO
- Beneficiary
- STATO MAGGIORE DELL'ESERCITO
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- IMPIANTI SPORTIVI PER GRUPPI SPORTIVI MILITARI
- Line
- Infrastrutture
- Action
- Infrastrutture pubbliche, didattiche/universitarie, sociali e sanitarie