CUP: B43H12000040007
COSTRUZIONE CONDUTTURA ACQUA POTABILE GRUB BACHER
Funding monitored
€ 117,148.46
of which cohesion funds
€ 0.00
Given name | Amount |
---|---|
Province | 117148.46 |
- Economies:
- € 24,643.54
- Other resources - Private:
- € 35,448
Payments monitored
€ 146,435.57
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 146435.57 | 146435.57 | 124 |
State of progress
Completed
Expected start: 30/04/2010
Effective start: 30/04/2010
Expected end: 30/09/2011
Effective end: 30/09/2011
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Environment
- Gestione e distribuzione d'acqua (potabile)
Territory
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- CONSORZIO DI MIGLIORAMENTO FONDIARIO PRANTACH
- Beneficiary
- CONSORZIO DI MIGLIORAMENTO FONDIARIO PRANTACH
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PAR FSC PA BOLZANO
- Line
- Servizio idrico: Efficienza del servizio idrico
- Action
- Servizio idrico: Efficienza del servizio idrico