CUP: D61B13000820006
VIABILITA DI SCORRIMENTO DA ROTOLO A PIAZZA EUROPA. VIA ROTOLO SISTEMAZIONE VIABILITA
SUMMARY OF THE PROJECT
VIABILITA DI SCORRIMENTO DA ROTOLO A PIAZZA EUROPA. VIA ROTOLO SISTEMAZIONE VIABILITA
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 1 km
- Achieved
- 1 km
Funding monitored
€ 16,000,000.00
of which cohesion funds
€ 16,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 16000000.00 |
Payments monitored
€ 109,931.04
of which cohesion funds
€ 109,931.04
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 6470.88 | 6470.88 | 0 |
2020 | 5304.00 | 11774.88 | 0 |
2021 | 0 | 11774.88 | 0 |
2022 | 98156.16 | 109931.04 | 0 |
State of progress
Open
Expected start: 01/07/2020
Effective start: not available
Expected end: 31/12/2021
Effective end: not available
Entities
- Planning body
- COMUNE DI CATANIA
- Implementing body
- COMUNE DI CATANIA
- Beneficiary
- COMUNE DI CATANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CITTA' METROPOLITANA DI CATANIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale