CUP: J17I10000040001

COMPLETAMENTO SCC ADRIATICA

Updated on 31/12/2018
Public cost € 78,000,000.00
Given name Amount
Status: other measures78000000.00
Payments € 55,776,753.61
Year Amount Cumulative amount Percentage on public financing
2010413100.00413100.000
2011842400.001255500.001
201270463.411325963.411
2013657957.761983921.172
20149590276.7311574197.9014
201515521468.4127095666.3134
201615902989.7742998656.0855
20176059677.5149058333.5962
20186718420.0255776753.6171

State of progress

Open
Expected start: 02/01/2015
Effective start: 25/02/2015
Expected end: 13/05/2019
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
RETE FERROVIARIA ITALIANA SPA
Beneficiario
RETE FERROVIARIA ITALIANA SPA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA ATTUATIVO SPECIALE FSC DIRETTRICI FERROVIARIE
Line
Direttrice ferroviaria Napoli Bari Lecce Taranto
Action
Direttrice ferroviaria Napoli Bari Lecce Taranto altre opere