CUP: J41H01000080008

RADDOPPIO FRASSO TELESINO - VITULANO

Updated on 30/04/2021
Funding monitored € 880,000,000.00 of which cohesion funds € 21,000,000.00
Given name Amount
Development and Cohesion Fund21000000.00
Status: other measures859000000.00
Payments monitored € 28,746,603.92 of which cohesion funds € 685,998.50
Year Amount Cumulative amount Percentage on public financing
20081275332.371275332.370
200901275332.370
201001275332.370
20111576623.722851956.090
201202851956.090
201302851956.090
2014520000.003371956.090
201589833.533461789.620
20164583077.158044866.770
20174010774.0912055640.861
20182246619.6014302260.461
20192171542.1116473802.571
20202640226.7219114029.292
20219632574.6328746603.923

State of progress

Open
Expected start: 07/12/2020
Effective start: 07/12/2020
Expected end: 14/01/2026
Effective end: not available

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
RFI SPA - RETE FERROVIARIA ITALIANA
Beneficiary
RFI SPA - RETE FERROVIARIA ITALIANA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA ATTUATIVO SPECIALE FSC DIRETTRICI FERROVIARIE
Line
Direttrice ferroviaria Napoli Bari Lecce Taranto
Action
Direttrice ferroviaria Napoli Bari Lecce Taranto altre opere

Other projects in territory