Updated on 31/12/2022
Funding monitored € 2,424,000,000.00 of which cohesion funds € 47,000,000.00
Given name Amount
Development and Cohesion Fund47000000.00
Status: other measures2377000000.00
Payments monitored € 111,041,293.48 of which cohesion funds € 2,153,028.38
Year Amount Cumulative amount Percentage on public financing
2016478400.00478400.000
20170478400.000
20180478400.000
20190478400.000
20200478400.000
202131529475.8132007875.811
202279033417.67111041293.484

State of progress

Open
Expected start: 28/09/2020
Effective start: 28/09/2020
Expected end: 18/07/2027
Effective end: not available

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
RETE FERROVIARIA ITALIANA SPA
Beneficiary
RETE FERROVIARIA ITALIANA SPA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA ATTUATIVO SPECIALE FSC DIRETTRICI FERROVIARIE
Line
Direttrice ferroviaria Napoli Bari Lecce Taranto
Action
Direttrice ferroviaria Napoli Bari Lecce Taranto altre opere

Other projects in territory