CUP: J11C09000000009

BARI SUD (BARI CENTRALE - BARI TORRE A MARE)

Updated on 28/02/2019
Public cost € 391,000,000.00
Given name Amount
Revolving Fund (Cohesion Action Plan)100000000.00
Status: other measures291000000.00
Payments € 95,146,810.94
Year Amount Cumulative amount Percentage on public financing
20092560143.782560143.780
201002560143.780
201151202.882611346.660
201202611346.660
20132204174.104815520.761
20141894368.406709889.161
20151727033.248436922.402
201637796661.9146233584.3111
201727785275.4474018859.7518
201818624875.4892643735.2323
20192503075.7195146810.9424

State of progress

Open
Expected start: 16/09/2019
Effective start: not available
Expected end: 30/07/2024
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
RFI SPA - RETE FERROVIARIA ITALIANA
Beneficiario
RFI SPA - RETE FERROVIARIA ITALIANA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA ATTUATIVO SPECIALE FSC DIRETTRICI FERROVIARIE
Line
Direttrice ferroviaria Napoli Bari Lecce Taranto
Action
Nodo di Bari: Bari Sud (CIS NA-BA)