CUP: J71H92000000007

RADDOPPIO PESCARA - BARI: TRATTA RIPALTA - LESINA

Updated on 31/12/2018
Public cost € 106,000,000.00
Given name Amount
Status: other measures98000000.00
Resources released8000000.00
Payments € 9,977,502.40
Year Amount Cumulative amount Percentage on public financing
2010282744.00282744.000
20113501173.983783917.983
2012733632.834517550.814
20131868670.816386221.626
2014233235.356619456.976
2015434755.007054211.976
20161410004.088464216.057
201780259.008544475.058
20181433027.359977502.409

State of progress

Open
Expected start: 27/12/2019
Effective start: not available
Expected end: 30/01/2023
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
RETE FERROVIARIA ITALIANA SPA
Beneficiario
RETE FERROVIARIA ITALIANA SPA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA ATTUATIVO SPECIALE FSC DIRETTRICI FERROVIARIE
Line
Direttrice ferroviaria Napoli Bari Lecce Taranto
Action
Direttrice ferroviaria Napoli Bari Lecce Taranto altre opere