CUP: E12I06000010006

ADEGUAMENTO SCHEMA FOGNARIO DEPURATIVO N. 223 - NUCLEO IND. TORTOL? -

Updated on 31/12/2018
Public cost € 3,890,000.00
Given name Amount
Development and Cohesion Fund3890000.00
Economies:
€ 110,000.00
Payments € 73,204.10
Year Amount Cumulative amount Percentage on public financing
20111308.241308.240
201210410.5711718.810
20138278.3919997.200
201421146.8041144.001
2015041144.001
2016959.3342103.331
201730363.5172466.841
2018737.2673204.101

State of progress

Open
Expected start: 01/06/2019
Effective start: not available
Expected end: 17/03/2020
Effective end: not available

Type

Theme

Territory

Entities

Planning body
REGIONE SARDEGNA - PRESIDENZA
Implementing body
ABBANOA S.P.A
Beneficiario
ABBANOA S.P.A
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC SARDEGNA
Line
6.2.1.B. Interventi per il servizio idrico integrato - Comparto fognario - depurativo
Action
Interventi EU pilot

Other projects in territory