CUP: H11B17000900006
COMPLETAMENTO DELLA REALIZZAZIONE DI PISTA CICLABILE SUL LUNGOMARE DI MARTINSICURO
SUMMARY OF THE PROJECT
COMPLETAMENTO DELLA REALIZZAZIONE DI PISTA CICLABILE SUL LUNGOMARE DI MARTINSICURO
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 722,197.76
of which cohesion funds
€ 722,197.76
Given name | Amount |
---|---|
Development and Cohesion Fund | 722197.76 |
- Economies:
- € 31,781.42
Payments monitored
€ 695,528.33
of which cohesion funds
€ 695,528.33
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 16417.36 | 16417.36 | 2 |
2019 | 0 | 16417.36 | 2 |
2020 | 264047.47 | 280464.83 | 38 |
2021 | 407447.09 | 687911.92 | 95 |
2022 | 7616.41 | 695528.33 | 96 |
State of progress
Completed
Expected start: 21/09/2020
Effective start: 12/10/2020
Expected end: 15/06/2021
Effective end: 19/07/2021
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI MARTINSICURO
- Beneficiary
- COMUNE DI MARTINSICURO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio