CUP: J19F14000030009

SEGGIOVIA QUADRIPOSTO "FONTARI-CAMPO IMPERATORE" UBICATA IN LOCALITA CAMPO IMPERATORE VIA LOCALITA CAMPO IMPERATORE SOSTITUZIONE DELLA SEGGIOVIA QUADRIPOSTO "FONTARI-CAMPO IMPERATORE" CON UNA SEGGIOVIA AD AMMORSAMENTO AUTOMATICO CON VEICOLI A 6 POSTI DENOMINATA "CAMPO IMPERATORE-OSSERVATORIO

Updated on 30/04/2020
Public cost € 2,421,489.24
Given name Amount
Development and Cohesion Fund2421489.24
Economies:
€ 78,510.76
Other resources - Private:
€ 5,373,720
Payments € 7,374,729.49
Year Amount Cumulative amount Percentage on public financing
20143791.583791.580
201503791.580
2016819.424611.000
20173694391.423699002.42152
20182066161.195765163.61238
20191609565.887374729.49304

State of progress

Completed
Expected start: 01/09/2017
Effective start: 01/09/2017
Expected end: 01/12/2018
Effective end: 01/12/2018

Type

Theme

Territory

Entities

Planning body
REGIONE ABRUZZO - GIUNTA REGIONALE
Implementing body
CENTRO TURISTICO GRAN SASSO S.P.A.
Beneficiary
CENTRO TURISTICO GRAN SASSO S.P.A.
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Promuovere la mobilità urbana sostenibile e la logistica urbana

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PAR FSC ABRUZZO
Line
III.2.1.a - Rafforzare e migliorare il sistema di mobilità regionale nei centri urbani e nelle aree montane attraverso l'incentivazione di mobilità di trasporto sostenibili (filovie, funivie, combinaz
Action
Intervento 2 - Migliorare l'accessibilità e la mobilità nei centri abitati e nelle aree montane attraverso modalità di trasporto sostenibile (filovie, funivie ecc.) e combinazioni intermodali

Other projects in territory