CUP: G89H16000000002
LAVORI DI RIPRISTINO OFFICIOSITA E SISTEMAZIONE IDRAULICA TORRENTE SERRAPOTAMO
SUMMARY OF THE PROJECT
MITIGAZIONE RISCHIO IDROGEOLOGICO
Implementation indicator
Estensione in lunghezza
- Target
- 2.60 km
- Achieved
- 0 km
Funding monitored
€ 800,000.00
of which cohesion funds
€ 800,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 800000.00 |
Payments monitored
€ 49,541.61
of which cohesion funds
€ 49,541.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 9632.44 | 9632.44 | 1 |
2021 | 20634.85 | 30267.29 | 3 |
2022 | 19274.32 | 49541.61 | 6 |
State of progress
Open
Expected start: 01/09/2023
Effective start: not available
Expected end: 31/03/2024
Effective end: not available
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMMISSARIO STRAORDINARIO DELEGATO PER LA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REGIONE BASILICATA
- Beneficiary
- COMMISSARIO STRAORDINARIO DELEGATO PER LA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REGIONE BASILICATA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico