CUP: J32J11000220001

CONSOLIDAMENTO IN LOCALITA' S. LEONE - CASTELLO - MONTE DEL COMUNE DI SALA CONSILINA (SA)

Updated on 28/02/2021
Funding monitored € 3,168,939.44 of which cohesion funds € 3,168,939.44
Given name Amount
Development and Cohesion Fund3168939.44
Economies:
€ 239,680.56
Payments monitored € 1,898,879.18 of which cohesion funds € 1,898,879.18
Year Amount Cumulative amount Percentage on public financing
201537514.0637514.061
20161861365.121898879.1859

State of progress

Open
Expected start: 15/02/2014
Effective start: 09/12/2015
Expected end: 15/02/2015
Effective end: 04/10/2016

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
REGIONE CAMPANIA
Implementing body
COMUNE DI SALA CONSILINA
Beneficiary
COMUNE DI SALA CONSILINA
Priority QSN
Valorizzazione delle risorse naturali e culturali per l'attrattività e lo sviluppo
General objective QSN
Valorizzare le risorse naturali, culturali e paesaggistiche locali, trasformandole in vantaggio competitivo per aumentare l'attrattività, anche turistica, del territorio, migliorare la qualità della vita dei residenti e promuovere nuove forme di sviluppo economico sostenibile
Specific objective QSN
Rafforzare la capacità di conservazione e gestione delle risorse naturali e culturali mediante la cooperazione territoriale

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC CAMPANIA
Line
Delibera CIPE 8/12 - Frane e Versanti
Action
Interventi di prevenzione e mitigazione dei rischi da dissesto idrogeologico

Other projects in territory