CUP: J61C06000050009

BRETELLA DI COLLEGAMENTO DA SOCCAVO A MOSTRA TRA LE FERROVIE CUMANA E CIRCUMFLEGREA : TRATTA MONTE S.ANGELO-PARCO SAN PAOLO (1°LOTTO - 1°E 2° STRALCIO FUNZIONALE E 2°LOTTO FUNZIONALE, COMPRESA LA REALIZZAZIONE DELLA STAZIONE DI PARCO S.PAOLO)

Updated on 31/08/2019
Public cost € 79,567,610.68
Given name Amount
Development and Cohesion Fund9572245.74
Status: other measures69995364.94
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 30/11/2014
Effective start: 29/09/2017
Expected end: 31/12/2020
Effective end: not available

Type

Theme

Territory

Entities

Planning body
REGIONE CAMPANIA
Implementing body
PRESIDENTE DELLA REGIONE CAMPANIA - COMMISSARIO STRAORDINARIO EX ART. 11 COMMA 18, L. 887/84
Beneficiary
PRESIDENTE DELLA REGIONE CAMPANIA - COMMISSARIO STRAORDINARIO EX ART. 11 COMMA 18, L. 887/84
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC CAMPANIA
Line
Delibera CIPE 62/2011 - Infrastrutture strategiche regionali e interregionali
Action
APQ "Sistemi di Mobilità - Atto aggiuntivo"