CUP: H11I12000010002
SISTEMA TRAMVIARIO LINEA 4 - LEOPOLDA - PIAGGE
SUMMARY OF THE PROJECT
REALIZZAZIONE LINEA 4 NELLA TRATTA FIRENZE STAZIONE LEOPOLDA - PIAGGE - SAN DONNINO - CAMPI BISENZIO
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 6 KM
- Achieved
- 0.01 KM
Funding monitored
€ 166,000,000.00
of which cohesion funds
€ 24,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 24000000.00 |
Another public source | 142000000.00 |
Payments monitored
€ 1,098,006.53
of which cohesion funds
€ 1,098,006.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 1098006.53 | 1098006.53 | 0 |
State of progress
Open
Expected start: 01/03/2022
Effective start: not available
Expected end: 01/08/2024
Effective end: not available
Entities
- Planning body
- COMUNE DI FIRENZE
- Beneficiary
- COMUNE DI FIRENZE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PATTO FIRENZE
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Trasporto sostenibile urbano