CUP: F11B15000580002

SS. SS. 85-87-645-647-650. ADEGUAMENTO E MESSA IN SICUREZZA DELLE FERMATE DEL TRASPORTO PUBBLICO LOCALE. LAVORI DI COSTRUZIONE DI N. 14 GOLFI DI FERMATA LUNGO LE STRADE STATALI DEL MOLISE

Updated on 30/06/2022
Funding monitored € 1,556,683.45 of which cohesion funds € 1,556,683.45
Given name Amount
Development and Cohesion Fund1556683.45
Economies:
€ 1,143,316.55
Payments monitored € 1,556,683.45 of which cohesion funds € 1,556,683.45
Year Amount Cumulative amount Percentage on public financing
2016113584.69113584.697
2017599635.69713220.3845
2018207406.19920626.5759
2019416971.141337597.7185
2020219085.741556683.45100

State of progress

Completed
Expected start: 19/10/2016
Effective start: 19/10/2016
Expected end: 30/04/2019
Effective end: 03/04/2019

Entities

Planning body
REGIONE MOLISE
Implementing body
ANAS SPA
Beneficiary
ANAS SPA
Executor
ITALCOEN
CON.AR.ED - CONSORZIO ARTIGIANI EDILI SCARL
ATI EDILSTRADE 2011 SRL - GEOGRIMP SRL - ELETTROSERVICE GROUP SRL
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PAR FSC MOLISE
Line
Viabilità di convergenza regionale ed interregionale
Action
Viabilità di convergenza regionale ed interregionale