CUP: F53D12000430003
SISTEMAZIONE STRADE DI COLLEGAMENTO S.P.
SUMMARY OF THE PROJECT
SISTEMAZIONE STRADE DI COLLEGAMENTO S.P.
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 300 m
- Achieved
- 300 m
Funding monitored
€ 393,063.41
of which cohesion funds
€ 393,063.41
Given name | Amount |
---|---|
Development and Cohesion Fund | 393063.41 |
- Economies:
- € 6,936.59
Payments monitored
€ 393,063.41
of which cohesion funds
€ 393,063.41
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 235901.57 | 235901.57 | 60 |
2017 | 0 | 235901.57 | 60 |
2018 | 157161.84 | 393063.41 | 100 |
State of progress
Completed
Expected start: 29/01/2015
Effective start: 29/01/2015
Expected end: 17/05/2016
Effective end: 17/05/2016
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI ROCCASICURA
- Beneficiary
- COMUNE DI ROCCASICURA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico