CUP: D48B11000080002
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT 'A' - PEU 20 SP 4
SUMMARY OF THE PROJECT
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT 'A' - PEU 20 SP 4
Implementation indicator
Volume oggetto di intervento
- Target
- 100 mc
- Achieved
- 100 mc
Funding monitored
€ 774,316.04
of which cohesion funds
€ 774,316.04
Given name | Amount |
---|---|
Development and Cohesion Fund | 774316.04 |
- Economies:
- € 4,992.19
Payments monitored
€ 774,316.04
of which cohesion funds
€ 774,316.04
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 77930.82 | 77930.82 | 10 |
2013 | 197792.26 | 275723.08 | 35 |
2014 | 249590.98 | 525314.06 | 67 |
2015 | 0 | 525314.06 | 67 |
2016 | 197289.06 | 722603.12 | 93 |
2017 | 0 | 722603.12 | 93 |
2018 | -1423.04 | 721180.08 | 93 |
2019 | 53135.96 | 774316.04 | 100 |
State of progress
Completed
Expected start: 31/10/2011
Effective start: 31/10/2011
Expected end: 15/11/2017
Effective end: 15/11/2017
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI TORELLA DEL SANNIO
- Beneficiary
- CONSORZIO PEU 20 (COMUNE DI TORELLA DEL SANNIO)
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico