CUP: H66G18000060002

VIABILITA INTERNA STRATEGICA - SS.PP. 76 "PONTONE", 68 "CHIAUCI" E 68/DIR PESCOLANCIANO

SUMMARY OF THE PROJECT

RIFACIMENTO, BONIFICA E SISTEMAZIONE DEL PIANO VIABILE DELLE SS.PP. 76 "PONTONE", 68 "CHIAUCI" E 68/DIR "PESCOLANCIANO

Implementation indicator

Lunghezza totale delle strade ricostruite o rinnovate

Target
1 KM
Achieved
1 KM
Updated on 30/06/2022
Funding monitored € 264,766.78 of which cohesion funds € 264,766.78
Given name Amount
Development and Cohesion Fund264766.78
Economies:
€ 15,233.22
Payments monitored € 256,591.45 of which cohesion funds € 256,591.45
Year Amount Cumulative amount Percentage on public financing
202028000.0028000.0010
2021182283.33210283.3379
202246308.12256591.4596

State of progress

Completed
Expected start: 04/06/2020
Effective start: 07/07/2020
Expected end: 03/11/2021
Effective end: 09/06/2021

Type

Theme

Territory

Entities

Planning body
REGIONE MOLISE
Implementing body
PROVINCIA DI ISERNIA
Beneficiary
PROVINCIA DI ISERNIA
Executor
F.LLI DI MENNA E FIGLI

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PATTO MOLISE
DCF strategic sector
Infrastrutture
DCF area axis
Infrastrutture di trasporto ferroviario e stradale