CUP: D71E16000300001
SISTEMA TRAM PALERMO - FASE II
SUMMARY OF THE PROJECT
PROGETTO DI REALIZZAZIONE DI TRE TRATTE TRAMVIARIE
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 21.60 KM
- Achieved
- 0 KM
Public cost
€ 198,872,027.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 198872027.00 |
Payments
€ 12,045,445.10
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 1235101.14 | 1235101.14 | 0 |
2019 | 10810343.96 | 12045445.10 | 6 |
State of progress
Open
Expected start: 01/03/2021
Effective start: not available
Expected end: 15/04/2026
Effective end: not available
Entities
- Planning body
- COMUNE DI PALERMO
- Implementing body
- COMUNE DI PALERMO
- Beneficiary
- COMUNE DI PALERMO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PATTO PALERMO
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Trasporto sostenibile urbano