CUP: J74J22000170001
ELETTRIFICAZIONE DELLA TRATTA FERROVIARIA CAGLIARI-ORISTANO
SUMMARY OF THE PROJECT
INTERVENTI DI ELETTRIFICAZIONE A 3 KV DELLA LINEA FERROVIARIA TRA CAGLIARI E ORISTANO
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 95 km
- Achieved
- 0 km
Funding monitored
€ 95,800,000.00
of which cohesion funds
€ 46,800,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 46800000.00 |
Another public source | 49000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/10/2023
Effective start: not available
Expected end: 30/11/2025
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- RETE FERROVIARIA ITALIANA SPA
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario