CUP: F41B10000740001

ADEGUAMENTO AL TIPO ¿B¿ (4 CORSIE) DELL¿ITINERARIO SASSARI ¿ OLBIALOTTO 3

Updated on 31/12/2018
Public cost € 123,512,000.00
Given name Amount
Development and Cohesion Fund123512000.00
Payments € 90,338,058.89
Year Amount Cumulative amount Percentage on public financing
201217924.7117924.710
2013191570.72209495.430
20143482886.803692382.232
201514358604.8518050987.0814
201628588624.1846639611.2637
201732061755.6578701366.9163
201811636691.9890338058.8973

State of progress

Open
Expected start: 07/08/2014
Effective start: 07/08/2014
Expected end: 31/01/2018
Effective end: 29/01/2018

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
ANAS S.P.A.
Beneficiario
ANAS S.P.A.
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC SARDEGNA
Line
Interventi sulla viabilità stradale
Action
CIS SS Sassari-Olbia - Lotto 0 - Adeguamento della S.S. 597/198