CUP: F71B07000460001

ADEGUAMENTO AL TIPO 'B' (4 CORSIE) DELL'ITINERARIO SASSARI ' OLBIA. LOTTO 9

Updated on 30/04/2020
Public cost € 37,125,000.00
Given name Amount
Development and Cohesion Fund18427615.24
Status: other measures18697384.76
Payments € 30,942,736.80
Year Amount Cumulative amount Percentage on public financing
201128240.4728240.470
20121739227.921767468.394
20133300133.955067602.3413
20149509350.1914576952.5339
20156396003.8820972956.4156
2016711712.9621684669.3758
20174952146.9226636816.2971
20183732207.3230369023.6181
2019571532.2030940555.8183
20202180.9930942736.8083

State of progress

Open
Expected start: 28/06/2012
Effective start: 28/06/2012
Expected end: 17/09/2018
Effective end: 17/09/2018

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
ANAS SPA
Beneficiary
ANAS SPA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC SARDEGNA
Line
Interventi sulla viabilità stradale
Action
CIS SS Sassari-Olbia - Lotto 0 - Adeguamento della S.S. 597/198