CUP: H76D16000170008
AMMODERNAMENTO E SISTEMAZIONE DELLE ZONE DI ENTRATA DELLA CABINOVIA MOLINO - LE BUSE - A.3.22M
SUMMARY OF THE PROJECT
AMMODERNAMENTO E SISTEMAZIONE DELLE ZONE DI ENTRATA DELLA CABINOVIA MOLINO - LE BUSE - A.3.22M
Implementation indicator
Estensione in lunghezza
- Target
- 1.74 km
- Achieved
- 1.74 km
Funding monitored
€ 34,044.30
of which cohesion funds
€ 34,044.30
Given name | Amount |
---|---|
Development and Cohesion Fund | 34044.30 |
- Other resources - Private:
- € 34,044
Payments monitored
€ 34,044.30
of which cohesion funds
€ 34,044.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 34044.30 | 34044.30 | 100 |
State of progress
Completed
Expected start: 13/06/2016
Effective start: 13/06/2016
Expected end: 31/10/2017
Effective end: 06/10/2017
Entities
- Planning body
- IMPIANTI FALCADE COL MARGHERITA SPA
- Implementing body
- IMPIANTI FALCADE COL MARGHERITA SPA
- Beneficiary
- IMPIANTI FALCADE COL MARGHERITA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE VENETO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Logistica