CUP: J23B11000480004
LAVORI DI SISTEMAZIONE INTERNA ED ESTERNA DELLA SCUOLA ELEM.
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 516,465.79
of which cohesion funds
€ 516,465.79
Given name | Amount |
---|---|
Development and Cohesion Fund | 516465.79 |
- Economies:
- € 41,034.21
Payments monitored
€ 480,753.97
of which cohesion funds
€ 480,753.97
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 36006.82 | 36006.82 | 6 |
2014 | 87616.78 | 123623.60 | 23 |
2015 | 350491.74 | 474115.34 | 91 |
2016 | 6638.63 | 480753.97 | 93 |
State of progress
Open
Expected start: 21/10/2014
Effective start: 21/10/2014
Expected end: 20/06/2015
Effective end: 30/11/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Education and training
- Infrastrutture per l'istruzione
Territory
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI MARIANO DEL FRIULI
- Beneficiary
- COMUNE DI MARIANO DEL FRIULI
- Executor
- COMUNE DI MARIANO DEL FRIULI
- Priority QSN
- Miglioramento e valorizzazione delle risorse umane
- General objective QSN
- Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
- Specific objective QSN
- Accrescere il tasso di partecipazione all'istruzione e formazione iniziale
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA ATTUATIVO MIUR MESSA IN SICUREZZA EDIFICI SCOLASTICI
- Line
- Riqualificazione e messa in sicurezza delle istituzioni scolastiche statali
- Action
- ulteriori interventi finanziabili ai sensi art. 18 DL 69/2013