CUP: H81F11000050005

(PAC) AEROPORTO DI LAMEZIA TERME - BRETELLA DI COLLEGAMENTO VIA DI RULLAGGIO CON TESTATA 28

Updated on 07/09/2020
Public cost € 5,307,656.42
Given name Amount
Revolving Fund (Cohesion Action Plan)5307656.42
Payments € 3,820,932.66
Year Amount Cumulative amount Percentage on public financing
201219760.0019760.000
201330245.7550005.750
201434221.4484227.191
20151785.7686012.951
20166068.7692081.711
201758487.00150568.712
2018458143.00608711.7111
20192630926.663239638.3761
2020581294.293820932.6671

State of progress

Open
Expected start: 01/07/2016
Effective start: 10/06/2016
Expected end: 15/10/2019
Effective end: 06/11/2019

Type

Theme

Territory

Entities

Planning body
ENAC S.P.A.
Implementing body
S.A.CAL S.P.A
Beneficiary
S.A.CAL S.P.A
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Programme
PROGRAMMA PAC MINISTERO DELLE INFRASTRUTTURE E TRASPORTI - SALVAGUARDIA INTERVENTI
Line
Salvaguardia
Action
Aeroporto di Bari Palese - Adeguamento infrastrutture di volo e prolungamento pista - Adeguamento RESA

Other projects in territory