CUP: J27I12000220001
RIPRISTINO ITINERARIO MERCI NAPOLI - BARI (A FOGGIA)
Funding monitored
€ 7,753,481.46
of which cohesion funds
€ 7,227,558.20
Given name | Amount |
---|---|
European Union | 5420668.65 |
Revolving Fund (National co-financing) | 1806889.55 |
Another public source | 525923.26 |
Payments monitored
€ 7,753,481.46
of which cohesion funds
€ 7,227,558.20
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 314805.95 | 314805.95 | 4 |
2014 | 1675050.60 | 1989856.55 | 25 |
2015 | 6215541.47 | 8205398.02 | 105 |
2016 | 525923.26 | 8731321.28 | 112 |
2017 | -977839.82 | 7753481.46 | 100 |
State of progress
Completed
Expected start: 26/06/2013
Effective start: 26/06/2013
Expected end: 12/02/2016
Effective end: 12/02/2016
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- RETE FERROVIARIA ITALIANA SPA
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- NOP CONV ERDF NETWORKS AND MOBILITY
- Axis
- Potenz. connessioni sistemi loc. sistema infr. sup.
- Operational objective
- Rafforzare le connessioni interne al sistema logistico portante e tra questo e i poli produttivi locali.