CUP: C81C11000100001
LAVORI DI PROLUNGAMENTO DEL SOTTOPASSO FERROVIARIO CON ANNESSO NODO INTERSETTORIALE PER LA MOBILITÃ
Funding monitored
€ 13,500,000.00
of which cohesion funds
€ 13,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 13500000.00 |
Payments monitored
€ 1,587,694.60
of which cohesion funds
€ 1,587,694.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 50000.00 | 50000.00 | 0 |
2016 | 400822.71 | 450822.71 | 3 |
2017 | 206444.07 | 657266.78 | 4 |
2018 | 39801.29 | 697068.07 | 5 |
2019 | 890626.53 | 1587694.60 | 11 |
State of progress
Open
Expected start: 24/01/2019
Effective start: 24/01/2019
Expected end: 31/12/2019
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI LECCE
- Beneficiary
- COMUNE DI LECCE
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC PUGLIA
- Line
- Trasporti
- Action
- Sistema ferroviario regionale