CUP: E68D03000000002

COMPLETAMENTO DEL SIFONE LECCESE RAMO IONICO-CONDOTTA DAL SERBATOIO DI S.PAOLO AL SERBATOIO DI SECLI

Updated on 31/08/2018
Public cost € 23,512,048.51
Given name Amount
European Union15988192.99
Revolving Fund (National co-financing)2727397.63
Region4796457.89
Other resources - Private:
€ 5,644,758
Payments € 23,512,048.45
Year Amount Cumulative amount Percentage on public financing
20078462.768462.760
20082183.1910645.950
200933264.5843910.530
20108091.1752001.700
201123550.0075551.700
201215664.1291215.820
20131382615.601473831.426
20145156719.476630550.8928
201516881497.5623512048.4599

State of progress

Completed
Expected start: 24/07/2014
Effective start: 24/07/2014
Expected end: 31/12/2015
Effective end: 31/12/2015

Type

Theme

  • Environment
  • Gestione e distribuzione d'acqua (potabile)

Territory

Entities

Planning body
REGIONE PUGLIA
Implementing body
ACQUEDOTTO PUGLIESE S.P.A.
Beneficiario
ACQUEDOTTO PUGLIESE S.P.A.
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF PUGLIA
Axis
RISORSE AMBIENTALI E ENERGETICHE PER LO SVILUPPO
Operational objective
1b) Creazione in via ordinaria di sistemi di adduzione e distribuzione integrati, dotati di specifici sistemi di accumulo e regolazione, tali da gestire ponderatamente il flusso delle portate di distribuzione alle singole utenze.