Updated on 31/08/2022
Funding monitored € 4,993,872.60 of which cohesion funds € 3,996,772.95
Given name Amount
European Union3395833.37
Revolving Fund (National co-financing)579289.22
Region1018750.01
Payments monitored € 2,528,018.17 of which cohesion funds € 2,528,018.17
Year Amount Cumulative amount Percentage on public financing
20141259.531259.530
20152526758.642528018.1750

State of progress

Open
Expected start: 03/08/2015
Effective start: 03/08/2015
Expected end: 16/12/2015
Effective end: 16/12/2015

Type

Theme

Territory

Entities

Planning body
REGIONE PUGLIA
Implementing body
FERROVIE APPULO LUCANE SRL
Beneficiary
FERROVIE APPULO LUCANE SRL
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Promuovere la mobilità urbana sostenibile e la logistica urbana

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF PUGLIA
Axis
RETI E COLLEGAMENTI PER LA MOBILITA'
Operational objective
4a) Realizzare in ambito urbano e regionale gli interventi infrastrutturali necessari al completamento delle connessioni tra reti ferro-stradali principali e nodi logistici e di trasporto, minimizzando gli impatti ambientali e sul territorio.