CUP: H47D18000640006

089_GONNESA_411_RIQUALIFICAZIONE ENERGETICA INTEGRATA SISTEMI EDIFICIO - IMPIANTO

SUMMARY OF THE PROJECT

SOSTITUZIONE INFISSI, SCHERMATURE SOLARI, SOSTITUZIONE PUNTUALE IMPIANTO DI ILLUMINAZIONE DA TRADIZIONALE A LED, INSTALLAZIONE POMPA DI CALORE ARIA-ACQUA E RIQUALIFICAZIONE INVOLUCRO

Updated on 31/12/2018
Public cost € 545,221.06
Given name Amount
European Union272610.53
Revolving Fund190827.37
Region81783.16
Payments € 3,857.98
Year Amount Cumulative amount Percentage on public financing
20183857.983857.980

State of progress

Open
Expected start: 04/09/2019
Effective start: not available
Expected end: 04/02/2020
Effective end: not available

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO

Theme

Territory

Entities

Planning body
REGIONE AUTONOMA DELLA SARDEGNA
Beneficiario
COMUNE DI GONNESA

Programming area

European Regional Development Fund (ERDF)
2014-2020 EU Structural Funds
Programme
POR FESR SARDEGNA
Axis
ENERGIA SOSTENIBILE E QUALITA'  DELLA VITA
Specific objective
RIDUZIONE DEI CONSUMI ENERGETICI NEGLI EDIFICI E NELLE STRUTTURE PUBBLICHE O AD USO PUBBLICO, RESIDENZIALI E NON RESIDENZIALI E INTEGRAZIONE DI FONTI RINNOVABILI