CUP: J33G09000270006
IMPIANTO IL09 N. 14983 - IMPIANTO DI ILLUMINAZIONE PUBBLICA COMUNE DI MONTRESTA
Funding monitored
€ 118,869.12
of which cohesion funds
€ 130,204.45
Given name | Amount |
---|---|
European Union | 57266.22 |
Revolving Fund (National co-financing) | 32688.06 |
Region | 16094.29 |
Another public source | 12820.55 |
- Economies:
- € 24,155.88
Payments monitored
€ 118,869.12
of which cohesion funds
€ 100,728.20
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 9038.37 | 9038.37 | 7 |
2013 | 109800.75 | 118839.12 | 99 |
2014 | 0 | 118839.12 | 99 |
2015 | 30.00 | 118869.12 | 100 |
State of progress
Completed
Expected start: 22/08/2012
Effective start: 22/08/2012
Expected end: 05/10/2012
Effective end: 10/11/2012
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI MONTRESTA
- Beneficiary
- COMUNE DI MONTRESTA
- Executor
-
TRO.LUX
CS ENGINEERING - ING. CARLO SOLINAS
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF SARDINIA
- Axis
- Asse 3 Energia
- Operational objective
- Promuovere il risparmio, la riduzione dell'intensità e l'efficienza energetica.
Other projects in territory
Same type of investment
INTEGRAZIONE DEL CENTRO VISITE DEL SIC A MONTRESTA NUOVE TECNOLOGIE PER LA GESTIONE DEL SIC | € 110,348 |