CUP: B89D13000010006

MARSALA 9.4.1. DEMOLIZIONE E RICOSTRUZIONE DI UN COMPLESSO RESIDENZIALE POPOLARE SITO NELLA VIA MAZARA DI MARSALA E RIQUALIFICAZIONE URBANA DEL CONTESTO N. 36 ALLOGGI

SUMMARY OF THE PROJECT

MARSALA 9.4.1. DEMOLIZIONE E RICOSTRUZIONE DI UN COMPLESSO RESIDENZIALE POPOLARE SITO NELLA VIA MAZARA DI MARSALA E RIQUALIFICAZIONE URBANA DEL CONTESTO

Implementation indicator

Abitazioni ripristinate in aree urbane

Target
30
Achieved
29
Updated on 28/02/2022
Funding monitored € 4,041,925.71 of which cohesion funds € 4,041,925.71
Given name Amount
Municipality1000000.00
Another public source3041925.71
Economies:
€ 958,074.29
Payments monitored € 3,807,658.79 of which cohesion funds € 3,807,658.79
Year Amount Cumulative amount Percentage on public financing
20141134.001134.000
201501134.000
20161565859.841566993.8438
20171307907.652874901.4971
2018932757.303807658.7994

State of progress

Open
Expected start: 02/02/2016
Effective start: 02/02/2016
Expected end: 31/12/2019
Effective end: 30/07/2018

Type

Theme

Territory

Entities

Planning body
REGIONE SICILIANA
Beneficiary
COMUNE DI MARSALA

Programming area

European Regional Development Fund (ERDF)
2014-2020 EU Structural Funds
Programme
POR FESR SICILIA
Axis
Inclusione Sociale
Specific objective
RIDUZIONE DEL NUMERO DI FAMIGLIE CON PARTICOLARI FRAGILITÀ SOCIALI ED ECONOMICHE IN CONDIZIONI DI DISAGIO ABITATIVO