CUP: F77H17001850001
LAVORI DI RISANAMENTO DELLA SOVRASTRUTTURA STRADALE IN TRATTI SALTUARI LUNGO LA SS 514 DAL KM 0+000 AL KM 41+000
SUMMARY OF THE PROJECT
RIPRISTINO DELLA PAVIMENTAZIONE STRADALE TRAMITE IL RIFACIMENTO DELLO STRATO D'USURA E DELLO STRATO DI BINDER E RIFACIMENTO DELLA SEGNALETICA ORIZZONTALE
Implementation indicators
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 6.15 km
- Achieved
- 6.15 km
Lunghezza totale delle strade ricostruite o rinnovate di cui: TEN-T
- Target
- 6.15 km
- Achieved
- 6.15 km
km di strade ristrutturate (core indicator n° 16)
- Target
- 6.15 km
- Achieved
- 6.15 km
- Slide 1
- Slide 2
- Slide 3
Funding monitored
€ 474,060.83
of which cohesion funds
€ 474,060.83
Given name | Amount |
---|---|
Development and Cohesion Fund | 474060.83 |
- Economies:
- € 175,939.17
Payments monitored
€ 387,577.26
of which cohesion funds
€ 387,577.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 387577.26 | 387577.26 | 81 |
State of progress
Open
Expected start: 15/11/2017
Effective start: 15/11/2017
Expected end: 02/01/2018
Effective end: 02/01/2018
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PATTO SICILIA
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture di trasporto ferroviario e stradale